Central County Emergency 911 New Building Project Week 6
- January 8, 2007 - Land is cleared and actual excavation begins.
January 9, 2007
- Excavation begins in earnest. Initial reports indicate a plan to dig down about 5' today.

January 10, 2007
- Excavation continues with a dozer, track hoe and 2 dump trucks. On site fuel tank delivered. Plans are to remove some of the fence around the tower to allow for shoring.

January 11, 2007
- 1030hrs - Excavation continues at full speed. Weather forecast calls for much colder temperatures and several days of rain after today.

Mid Day Update
- 1319 - Excavation continues. Gravel delivered in preparation for sewer line installation.

End of Day Update [Next update will be Wed Jan 17 due to weather and call
load]
- First dirt stockpile is full. Second pile started on the west side of current building.