Central County Emergency 911 New Building Project Week 4
- December 24-30 Status. Still awaiting final permit from MSD .
- First piece of construction equipment delivered to the site. Hitachi Excavator Zaxis 225.
- December 29, 2006 - More equipment delivered and property is staked for
anticipated dirt work on January 2, 2007