Updated:06/04/2007 06:11:26 PM
Central County Emergency 911 New Building Project Week 26
- May 31, 2007 - Pictures inside the new building.
- June 2, 2007 - Finishing up the second floor work after pouring the
concrete. Masonry work starts next week. Storm sewer installed from parking
lot towards detention pond.