Updated:02/15/2007 02:48:44 PM
Central County Emergency 911 New Building Project Week 12
- February 19, 2007 - Snow is melting rapidly. Crews began installation of the forms for the footings and poured some concrete as well.
- February 20, 2007 - Forms are taken off the footings poured yesterday. Forms and concrete placed on the other side of the north footing.

- February 23, 2007 - Concrete poured on portions of two basement walls.